When a hospital project moves forward, its progress is rarely visible from the outside. What people do notice is the paperwork: contracts, signatures, budgets and reviews. This week, the approval by the Comptroller General’s Office (Contraloría General de la República) of a contract with the Costa Rican Social Security Fund (Caja Costarricense de Seguro Social, CCSS) brought the Hospital México tower into the spotlight, one of the most talked-about hospital infrastructure projects at the moment.
According to Delfino.cr, the Contraloría granted its endorsement (refrendo) to the contract between the CCSS and the company Edica Limitada for $27,955,000. Other outlets, such as AM Prensa, described it as the basis for building a new tower. Both agree that the approval is a preliminary step: construction has not yet begun. To understand what this step involves, it helps to review what was approved, what will be built and what remains pending.
What an endorsement is and why it matters
The endorsement (refrendo) is a control that the Contraloría applies to certain public contracts before they can be carried out. Put simply, the body checks that the procurement process complies with the regulations and that the commitment of public money is backed up before the project starts.
That is why the approval does not mean work will start. According to the sources, the CCSS still has to issue the start order. From that point on, the timelines begin to run, and the company must submit updated schedules detailing physical and financial progress. The approval enables the next step; it does not complete it.
A turnkey project: what the company takes on
The contract was signed under the turnkey modality. This means a single company is responsible for the entire process: design, construction, equipment and commissioning. According to the Delfino.cr report, Edica must also train CCSS staff and provide comprehensive maintenance for the infrastructure and equipment.
For the institution, the advantage is that responsibility rests with a single contractor. For readers, the key point is the timeline: the contract lasts 36 months. The first 12 months cover design, construction and equipment; the remaining 24 correspond to maintenance, counted from the receipt of the installed goods and systems.
What will be enabled
According to the distribution of spaces that hospital authorities announced in September, as reported by Delfino.cr, the fourth and fifth floors of the tower would be set up as follows:
- Fourth floor: 24 intermediate care beds and 10 medical isolation cubicles.
- Fifth floor: 14 beds for the Coronary Care Unit, eight beds for hemodynamics, six beds for the Stroke Unit, and two angiographs.
It is worth looking at some of these terms. Intermediate care serves patients who need more monitoring than a general ward but not the level of an intensive care unit. The Coronary Care Unit and the Stroke Unit are specialized areas for patients with heart attacks and strokes, respectively. Hemodynamics refers to procedures that evaluate and treat blood flow in the heart and vessels, and the angiograph is the equipment that allows those vessels to be visualized during such procedures.
In other words, the project aims to add capacity in areas of high demand and complexity. The Delfino.cr report also notes that the work would be carried out on an existing building, so the CCSS would not need to purchase additional land.
The money: budget, guarantee and schedule
The endorsement document, identified as 8172026000000084, includes a budget certification issued on May 4 by the CCSS Infrastructure and Technology Management. According to that certification, the institution has scheduled ₡13,947.5 million to finance the project over four years.
One detail changes the reading: according to the CCSS, clarified during the process before the Contraloría, the contract will not generate budget commitments or disbursements for the rest of 2026. Most of the funds are planned for 2028. This means the heaviest spending will not come right away, but as the work progresses.
In addition, the company provided a performance guarantee of ₡635.6 million in favor of the CCSS, which must remain valid for the duration of the contract. This type of guarantee serves to ensure that the contractor fulfills what was agreed.
The timeline of the process
The sources provide dates that are worth putting in order. According to the Delfino.cr report, the CCSS awarded the works to Edica through official letter GIT-0945-2026, dated June 8. The award was based on the offer meeting the administrative, legal and technical requirements, and on the price being considered reasonable. The contract was signed on September 21 by Edica’s representative, Carlos Manuel Barrantes Araya, and two days later by the CCSS Infrastructure and Technology Manager, Jorge Alberto Granados Soto.
The process, therefore, has taken months. This sequence is normal in public procurement for works of this size, where each stage has its own requirements. What is still unclear, according to the available sources, is the exact date when construction will begin.
When to see a health professional
This project does not entail immediate changes in patient care, so there are no personal actions to take based on this news. However, it is worth remembering that symptoms of a heart attack or stroke require urgent attention. Among the signs that general guidelines from health organizations recommend not ignoring are chest pain or pressure, difficulty breathing, sudden weakness on one side of the body, drooping on one side of the face, and difficulty speaking. If any of these occur, the appropriate step is to call emergency services immediately, without waiting to see whether the condition improves on its own. For questions about your own health, consult a professional, not the information in a news article.
Key takeaways
- The Contraloría endorsed the CCSS contract with Edica for $27,955,000 to fit out floors of the Hospital México tower.
- The approval is a preliminary step: the CCSS must issue the start order for the timelines to begin.
- The contract lasts 36 months: 12 for design, construction and equipment, and 24 for maintenance.
- The project provides for intermediate care beds, isolation, a Coronary Care Unit, hemodynamics and a Stroke Unit.
- Most of the budget, ₡13,947.5 million over four years, is concentrated in 2028; there will be no disbursements for the rest of 2026.
This content is for informational purposes only and does not replace the advice of a health professional.
News sources
- Delfino.cr: Contraloría avala contrato por $27,95 millones para completar torre del Hospital México
- AM Prensa: ¡Avanza proyecto millonario! Hospital México podrá dar el siguiente paso para construir nueva torre
- Radio Monumental: Contraloría da luz verde a contrato para la construcción de nueva torre del Hospital México